Thursday, 25 May 2017

Critical Path Analysis





Critical path analysis uses network diagrams to identify:

The minimum time needed to complete a project.

Activities on the 'critical path' which cannot be delayed if the project is to finish on time.

Non critical activities.

How it works, advantages and disadvantages - details here.


Total Float time:

The amount of time by which a task can be delayed without causing the project to be delayed.

It can be calculated as:

LFT of activity minus EST of activity minus duration of activity.
The total float is found by subtracting the EST and the duration from the LFT, so for task B it would be 3 (13-4-6), this is the total float up to that activity.